Most people know that cutting into a shared wall needs a party wall notice. Far fewer know that digging near a neighbour’s building needs one too, even when you never touch their property and never go near the boundary wall.
This is Section 6 of the Party Wall etc. Act 1996, and it catches more projects than any other part of the Act.
The two rules
The 3 metre rule. If you are excavating within 3 metres of a neighbouring building or structure, and your excavation will go deeper than the bottom of their foundations, notice is required.
The 6 metre rule. If you are excavating within 6 metres of a neighbouring building, and your excavation falls below an imaginary line drawn downwards at 45 degrees from the bottom of their foundations, notice is required.
The 6 metre rule surprises people most. You could be a long way from the boundary and still be notifiable, because a deep excavation cuts into that 45 degree zone of influence. Deep foundations, piling and basement digs frequently trigger it.
Both rules measure to the neighbour’s building or structure, not to the boundary line. A neighbour whose extension sits close to the boundary brings their foundations closer to your works than the boundary position suggests.
What typically triggers it
- Extension foundations, particularly on sloping sites in the Cotswolds where one side is dug well down
- Basement excavation and lowering a cellar floor
- Underpinning
- New foundations for a garage or outbuilding
- Piling
- Drainage runs and soakaways, which often go deeper than people expect
- Removing a retaining structure
The honest summary: if you are digging anywhere near a neighbouring building and going down any appreciable depth, it is worth checking rather than assuming.
Why the Act bothers with it
Excavating near a foundation removes lateral support from the soil holding it up. Depending on the ground, that can cause settlement in the neighbouring structure, and the cracking that follows may appear weeks or months after the digging finished.
Clay soils are the usual concern, since they move with moisture content. Older buildings are more vulnerable because their foundations are typically shallow by modern standards, which is a live issue on the period property we survey across the Cotswolds and Bath, where a Victorian terrace may be sitting on very little.
Section 6 exists so that this is anticipated, recorded and dealt with rather than argued about afterwards.
What the process involves
Notice. One month’s notice to the adjoining owner, with plans and sections showing the depth and position of the excavation. The notice has to state whether you propose to strengthen or safeguard their foundations.
Their response. Fourteen days to consent or dissent. If they do not reply, dissent is deemed and surveyors are appointed.
A schedule of condition. This is the part that protects both sides, and we would always want it done. We record the condition of the neighbouring property before any digging starts, with photographs. If cracking appears later, that record settles whether it was there before.
The award. Sets out how the work will proceed, what protective measures apply, and how any damage will be dealt with.
Monitoring, where the risk warrants it. On deeper excavations, level monitoring during the works gives early warning of movement.
Getting it wrong
Starting without notice does not just risk a dispute, it removes the mechanism designed to protect you. Without a schedule of condition, any pre-existing crack in the neighbour’s wall becomes your problem to disprove, and that is a difficult position to argue from.
The other common error is relying on a builder’s view. Plenty of good builders are not familiar with Section 6, because it is less visible than cutting into a party wall, and the answer we hear most is that notice is not needed when it is.
Our party wall surveyors page sets out how we act, and our guides on when you need a party wall notice and party wall awards cover the wider process. If you are planning to dig, contact us before the digger arrives rather than after.
Frequently asked questions
Yes. Section 6 is about excavation near a neighbouring structure. It applies whether or not there is a shared wall involved.
You often do not, which is part of the problem. A trial hole on your own side gives an indication, and on older property the prudent assumption is that they are shallow.
The work proceeds without an award. You lose the protection of a schedule of condition, which on an excavation case is the thing most worth having.
It can, where that wall is a structure capable of being affected. It depends on the wall and the excavation.