Contract Administration and JCT Building Contracts

·

Most disputes between owners and builders come from the same place: there was no proper contract, no agreed scope, and nobody independent deciding whether the work done matched what was asked for.

What a building contract is actually for

A written contract isn’t about distrust. It’s about having answered the questions that will come up, before they come up.

A JCT contract – the standard forms used across most of UK construction – sets out:

  • What is being built, by reference to drawings and a specification
  • For how much, and how and when payment is made
  • By when, and what happens if that date is missed
  • Who decides whether the work is satisfactory
  • How changes are handled, because there are always changes
  • What happens if something unexpected is found
  • What the position is at completion, and the defects period afterwards

Without those answered, every one becomes a negotiation at the point it arises, which is the worst time to negotiate.

JCT publishes a range of forms for different project sizes, from a short Minor Works form suitable for a domestic project up to full forms for larger contracts. Picking the right one matters: an over-complicated contract on a small job creates administration nobody does, and an inadequate one on a large job leaves the important questions unanswered.

What the contract administrator does

The contract administrator is named in the contract and administers it impartially between the parties. The role is not the client’s representative, which surprises some clients, and that impartiality is what gives the decisions weight.

Before work starts: preparing the contract documents, agreeing the form, and getting the drawings and specification into a state where they describe one thing rather than several.

During the works:

  • Inspecting as the work proceeds, at appropriate stages
  • Issuing instructions where something needs to change, and valuing the effect
  • Certifying payment, which means valuing what has actually been done rather than what has been invoiced
  • Dealing with claims for additional time or money
  • Keeping the record of what was instructed and when

At the end: certifying practical completion, preparing the schedule of defects, and certifying the final account.

Why certification matters

Payment certification is the part that most changes how a project runs.

When the client pays against invoices, there is no independent check that the work has been done, or done properly. Overpayment early in a project is the single biggest risk to a client, because the leverage goes with the money.

When payment is certified against measured progress, the client pays for what exists. That protects both parties: the contractor gets paid properly and on time for work done, and the client isn’t funding work that hasn’t happened.

Where it goes wrong without one

  • Scope that was never written down, so both sides remember it differently
  • Variations agreed on site with no record of the cost, which arrive as a surprise at the end
  • Payment ahead of progress, leaving no money to finish with if the contractor leaves
  • No agreed completion date, so delay has no consequence
  • Defects at the end with no retention held and no mechanism to get them done

The documents come first

Contract administration only works if there’s something to administer. A contract referring to a vague specification produces vague results.

That’s why the specification and schedule of works matter as much as the contract itself: they’re what defines what is being paid for. See our surveying and design page, and our guide to remodelling from survey to design.

Where the building is listed or in a conservation area, the specification carries more weight again. See listed building consent.

Talk to us

We act as contract administrator on JCT building contracts, and prepare specifications and schedules of works, across the Cotswolds, Gloucestershire and Bath. Get in touch to discuss a project.

Frequently asked questions

Do I need a formal contract for a domestic project?

Any project where significant money changes hands benefits from one. JCT publishes a short Minor Works form intended for exactly this.

Is the contract administrator working for me?

The contract administrator is appointed by the client but administers the contract impartially between the parties. That impartiality is what makes the certificates mean something.

What is practical completion?

The point at which the works are complete enough for the client to take possession, apart from minor defects. It starts the defects liability period and usually releases part of the retention.